New switches being laid at Azerbaijan’s Mingachevir railway station
Trend:
The work to lay five new switches has started at the Mingachevir railway station in Azerbaijan, the Public Relations Department of the Azerbaijan Railways CJSC said in a message May 2.
The work is being carried out as part of the overhaul of the 600-kilometer section of the Baku-Boyuk Kasik railway.
The process of replacing switches at the Baku-Boyuk Kasik railway has been going on since September 2016.
The first new railroad switch was installed Sept. 9, 2016.
“So far, 150 new railroad switches have been installed,” the message said.
The contract envisages material and technical supply and overhaul of 600 kilometers of the Baku-Boyuk Kasik railway.
The project to overhaul the 600-km Baku-Boyuk Kasik railway was launched in October 2015.
--
Follow us on Twitter @AzerNewsAz
Here we are to serve you with news right now. It does not cost much, but worth your attention.
Choose to support open, independent, quality journalism and subscribe on a monthly basis.
By subscribing to our online newspaper, you can have full digital access to all news, analysis, and much more.
You can also follow AzerNEWS on Twitter @AzerNewsAz or Facebook @AzerNewsNewspaper
Thank you!