BTC expansion to cost $70m: energy exec
Expansion of the Baku-Tbilisi-Ceyhan (BTC) main export pipeline
is estimated at $69 million, says an executive of BP, which built
and operates the $4 billion conduit pumping Caspian oil to world
markets.
BP Azerbaijan Vice-President Rashid Javanshir said Tuesday that
boosting the throughput capacity from 1 million bpd to 1.2 million
bpd will be achieved by pumping a special polymer into the
pipeline.
"This is a simple and low-cost way of expanding the capacity of the
pipeline. The target of 1.2m bpd is to be reached by the year-end,
when daily production from ACG [the Azeri-Chirag-Gunashi fields in
the Azeri sector of the Caspian Sea] reaches 1m bpd," Javanshir
told a news conference.
About 800,000 bpd are currently transported through the
pipeline.
"Besides increasing the bulk of transported oil, expanding the
throughput capacity will allow to increase the company's
flexibility in refurbishment and other operations," Javanshir
said.
He dismissed rumors that BP and the state oil company SOCAR had
differences on the matter.
The BP executive said the board of directors of the pipeline
consortium BTC Co. had passed a decision on March 6 to increase the
BTC capacity. "Certain discussions are held all the time, but I
would not call them differences."
"There are documents concerning construction, running and expanding
the BTC, which have been ratified by the parliaments of the
countries participating in the project, and BP operates strictly
within the frames of standing agreements," Javanshir said.
SOCAR vice-president Elshad Nasirov earlier said the two companies
had differences.
The pipe's capacity may further be brought to 1.6m bpd after
2009.
Azeri Light oil has been exported to world markets via the BTC
pipeline since April 2007. 28m tons of oil was transported last
year, while the overall volume of oil pumped through the conduit
amounts to 45m tons. The cost-value of a barrel of Azeri Light
crude is $2.
The 1,768km BTC pipeline stretches from the Azeri Sangachal
terminal to the Turkish Mediterranean port of Ceyhan through
Georgia. 443 km of the pipe pass through Azerbaijan, 249km via
Georgia and 1,076 km through Turkey.
Here we are to serve you with news right now. It does not cost much, but worth your attention.
Choose to support open, independent, quality journalism and subscribe on a monthly basis.
By subscribing to our online newspaper, you can have full digital access to all news, analysis, and much more.
You can also follow AzerNEWS on Twitter @AzerNewsAz or Facebook @AzerNewsNewspaper
Thank you!